Hall and Kay Fire Engineering

Portwest Clothing

We were chosen to design, supply, install and commission the sprinkler systems, which involved installing the installation over of in excess of 7,500 Sprinklers throughout the building.

Sector

Manufacturing

Client: Simpson of York

We were chosen to design, supply, install and commission the sprinkler systems, which involved installing the installation over of in excess of 7,500 Sprinklers throughout the building.

Location

Yorkshire

Standard

FM global data sheets 8-9 & 8-34

Installation requirements

  • Sprinkler heads: 7,500
  • Fire pumps: 2x FM Diesel Fire pumps rated to 2000 USGPM
  • Tank: 4x 279m3

Programme

1 year

Year of completion

2023

Portwest Clothing is a global manufacturer and innovator of workwear, safety wear and PPE. This project involved installing sprinkler protection for their new High Bay Warehouse and protection for their Very Narrow Aisle Racking (VNA) system.

We were chosen to design, supply, install and commission the sprinkler systems, which involved installing the installation over of in excess of 7,500 Sprinklers throughout the building.

The system is designed to comply with the requirements of FM global database sheets 8-9 and 8-34. The sprinkler system incorporates a unique water supply consisting of 4x 280m 3 water storage tanks, providing a 2-hour water supply to the site to support VNA racking, mini load racking and an auto store.       
  
Our project manager, Jordan Saywood, said, “It was a privilege to be involved in a project this unique. We are really pleased with the finished product and working with the team at Simpsons of York and the broader project team really has been a pleasure.”

Lee Hunter the clients’ Project manager said “Hall & Kay have been very supportive throughout the design and construction phase of the project. In addition, their help with the insurers' fire engineers were indispensable.”

“Hall & Kay have been spot on. In the design at the start and on
site. The installation has been smooth and very quick.”

Jon Calvert

Simpson of York

Related industrial, manufacturing & warehousing case studies…

Thatchers Cider

Thatchers Cider

Hall & Kay are proud to install systems for Thatchers new state-of-the-art manufacturing facility. Read more

Musgraves, Dublin

Musgraves, Dublin

Hall & Kay are proud to install 32,000+ sprinklers in this fast-track 12-month project. Read more